Probis
Demo buchen
Mandate für Flughafenprogramme
München, Deutschland
·
Flughafen
Project

Flughafenmandate, einschließlich Terminal 2 München.

Kostencontrolling und Reporting für Kundenprojekte; bei Flughafenprojekten berichtet der Berater in die Struktur des Betreibers, sodass der Kunde einen einheitlichen Status sieht.

Overview
Invoices
Exam
Approval
Costs
Report
Budget
€104.5M
Committed
€101.3M
Invoiced
€66.9M
Forecast var.
+1.2%
Airport program mandates
Mandate für Flughafenprogramme
Incoming invoices
New
RE-2026-0418
Rohbau Nord GmbH · PDF
Contract
300.01 Structural Work
Gross amount
184,200.00 €
Service period
09/2026
✓ Data detected
→ Assigned to a contract
Cash-out plan
Plan · Actual · Outflow
M1
M6
M12
M18
M24
Costs
2 of 4 on budget
PackageBudgetFcst.Status
Shell & core€38.2M€38.0MOn budget
Facade€14.6M€15.3MReview
MEP€27.9M€28.4MReview
Fit-out€16.4M€16.4MOn budget
Forecast at completion €105.8M. Illustrative screen with fictional demo data.
Cost per m²
€3,480
Benchmark
€3,410
Cost items
312
Comparables
18
Airport program mandates
Mandate für Flughafenprogramme
Estimate vs median
Shell
Facade
MEP
Fit-out
Estimate
Median
Cost per m² vs comparables
18 projects
Low
Median
High
Cost groups
3 of 4 in range
Cost groupEstimateMedianStatus
Shell & core€38.2M€37.6MIn range
Facade€14.6M€13.4MAbove
MEP€27.9M€27.1MIn range
Fit-out€16.4M€16.9MIn range
Estimate €104.5M, benchmarked against 18 comparable projects. Illustrative screen with fictional demo data.
Projects
4
Total budget
€412M
Early warnings
2
Funding cover
96%
Airport program mandates
Mandate für Flughafenprogramme
Early warning
New
EW-2026-007
Riverside Campus · MEP package
Forecast drift
+7.1%
Owner
Project lead
Decision due
11/2026
✓ Flagged automatically
→ Assigned to an owner
Budget by project
Budget · Forecast
Northwind
Harbor
Elm St
Riverside
Portfolio
2 early warnings
ProjectBudgetVarianceStatus
Northwind Yards€104.5M+1.2%On budget
Harbor Point€138M+3.8%Review
Elm Street Lofts€61M−0.4%On budget
Riverside Campus€108M+7.1%Early warning
Two early warnings raised, each with a named owner and decision date. Illustrative screen with fictional demo data.
Bids received
5
Budget line
€14.6M
Lowest vs budget
−3.4%
Change orders
6
Airport program mandates
Mandate für Flughafenprogramme
Change orders
2 new
CO-2026-016
Facade package · Meridian Facades
Reason
Glazing spec change
Amount
+124,000.00 €
Tracked to date
6 · 420,000 €
✓ Within budget line
→ Awaiting approval
Bids vs budget line
€14.6M budget
Bid 1
Bid 3
Bid 5
Facade package award
Awarded €14.3M
BidderBidvs budgetStatus
Alder Facades€14.1M−3.4%Non-compliant
Meridian Facades€14.3M−2.1%Awarded
Kestrel Envelope€14.8M+1.4%Shortlist
Norland Glass€15.9M+8.9%Declined
Awarded €14.3M against a €14.6M budget line. Illustrative screen with fictional demo data.
WSP
Client
Control
Contract
Manage
The project

The project, in numbers.

Kostencontrolling und Reporting für Flughafenmandate, darunter Terminal 2 des Flughafens München.

Kostencontrolling und Reporting für Kundenprojekte; bei Flughafenprojekten berichtet der Berater in die Struktur des Betreibers, sodass der Kunde einen einheitlichen Status sieht. Eigene geschützte Instanz.

Location
München, Deutschland
Timeframe
Asset class
Flughafen
Scope
Kostencontrolling und Reporting für Flughafenmandate, berichtet in die Struktur des Betreibers.
Client
WSP
  • 650 Mio. € Investition Satellit Terminal 2
  • 11 Mio. Zusätzliche Passagiere pro Jahr
  • 27 Zusätzliche Gebäudepositionen
On the platform

The modules behind this project.

The PROBIS modules used on this project, shown on illustrative screens with demo data.

Control
Forecast vs. actual reconciled continuously, line item by line item.
Contract
Contracts and commitments tracked from pre-construction, not from the first invoice.
Manage
Ongoing asset and facility management once the project is in operation.
app.prob.is/projects/
wsp-airport-program-mandates
Overview
Invoices
Exam
Approval
Costs
Report
Budget
€104.5M
Committed
€101.3M
Invoiced
€66.9M
Forecast var.
+1.2%
Airport program mandates
Mandate für Flughafenprogramme
Incoming invoices
New
RE-2026-0418
Rohbau Nord GmbH · PDF
Contract
300.01 Structural Work
Gross amount
184,200.00 €
Service period
09/2026
✓ Data detected
→ Assigned to a contract
Cash-out plan
Plan · Actual · Outflow
M1
M6
M12
M18
M24
Costs
2 of 4 on budget
PackageBudgetFcst.Status
Shell & core€38.2M€38.0MOn budget
Facade€14.6M€15.3MReview
MEP€27.9M€28.4MReview
Fit-out€16.4M€16.4MOn budget
Forecast at completion €105.8M. Illustrative screen with fictional demo data.
Cost per m²
€3,480
Benchmark
€3,410
Cost items
312
Comparables
18
Airport program mandates
Mandate für Flughafenprogramme
Estimate vs median
Shell
Facade
MEP
Fit-out
Estimate
Median
Cost per m² vs comparables
18 projects
Low
Median
High
Cost groups
3 of 4 in range
Cost groupEstimateMedianStatus
Shell & core€38.2M€37.6MIn range
Facade€14.6M€13.4MAbove
MEP€27.9M€27.1MIn range
Fit-out€16.4M€16.9MIn range
Estimate €104.5M, benchmarked against 18 comparable projects. Illustrative screen with fictional demo data.
Bids received
5
Budget line
€14.6M
Lowest vs budget
−3.4%
Change orders
6
Airport program mandates
Mandate für Flughafenprogramme
Change orders
2 new
CO-2026-016
Facade package · Meridian Facades
Reason
Glazing spec change
Amount
+124,000.00 €
Tracked to date
6 · 420,000 €
✓ Within budget line
→ Awaiting approval
Bids vs budget line
€14.6M budget
Bid 1
Bid 3
Bid 5
Facade package award
Awarded €14.3M
BidderBidvs budgetStatus
Alder Facades€14.1M−3.4%Non-compliant
Meridian Facades€14.3M−2.1%Awarded
Kestrel Envelope€14.8M+1.4%Shortlist
Norland Glass€15.9M+8.9%Declined
Awarded €14.3M against a €14.6M budget line. Illustrative screen with fictional demo data.
Projects
4
Total budget
€412M
Early warnings
2
Funding cover
96%
Airport program mandates
Mandate für Flughafenprogramme
Early warning
New
EW-2026-007
Riverside Campus · MEP package
Forecast drift
+7.1%
Owner
Project lead
Decision due
11/2026
✓ Flagged automatically
→ Assigned to an owner
Budget by project
Budget · Forecast
Northwind
Harbor
Elm St
Riverside
Portfolio
2 early warnings
ProjectBudgetVarianceStatus
Northwind Yards€104.5M+1.2%On budget
Harbor Point€138M+3.8%Review
Elm Street Lofts€61M−0.4%On budget
Riverside Campus€108M+7.1%Early warning
Two early warnings raised, each with a named owner and decision date. Illustrative screen with fictional demo data.
Control
Contract
Manage
The client
WSP

Ingenieur- und Beratungsunternehmen mit Hauptsitz in Montreal, tätig in Planung, Beratung und Programmmanagement für Infrastruktur, Gebäude und Energie.

View client

Ein Flughafenprogramm mit Tabellen steuern?

Want the same control on your next project?